Illegal chainsaw operators have reportedly caused damage to a critical 330kV transmission line linking Aboadze to Anwomaso, resulting in power supply interruptions in parts of the Western and Ashanti Regions.
The incident occurred in the late afternoon of Wednesday, November 25, 2026, after a large tree felled by chainsaw operators landed on a section of the transmission line, causing it to trip and disrupting electricity supply.
The Ghana Grid Company Limited (GRIDCo), in a press statement issued on the same day, disclosed that the incident had affected the transmission line and forced system operators to reduce power supplied to parts of Kumasi due to the unavailability of the critical infrastructure.
According to GRIDCo, its engineers immediately commenced investigations following the trip and conducted patrols along the affected section of the transmission line to establish the cause of the disruption.
The investigations subsequently revealed that the damage was caused by a tree that had been felled by chainsaw operators onto the transmission infrastructure.
The incident has raised concerns over the activities of illegal chainsaw operators and the potential dangers their operations pose to critical national infrastructure, particularly electricity transmission facilities.
The Aboadze-Anwomaso 330kV transmission line is an important component of Ghana’s power transmission network, and its disruption has affected electricity supply to consumers in parts of the two regions.
GRIDCo said the situation had compelled system operators to reduce power supplied to parts of Kumasi while efforts were being made to address the damage and restore the affected transmission line.
Engineers Working To Restore Power
The power transmission company has assured affected consumers that its engineers are working diligently to repair the damaged line and restore normal electricity supply as quickly as possible.
In the statement, GRIDCo said every effort was being made to remedy the situation, adding that the necessary repairs were underway to ensure the affected transmission line was returned to service.
The company apologised to consumers who had been affected by the disruption and assured the public that electricity supply would be restored once the repairs were completed.
The incident is expected to cause inconvenience to households, businesses and institutions in the affected communities, particularly in parts of Kumasi where power supply has been reduced because of the damage.
GRIDCo, however, did not indicate in the statement the exact time by which repairs would be completed or normal electricity supply fully restored.
The company urged affected consumers to bear with it as engineers continue working to repair the damaged transmission infrastructure.
The statement was issued by the Corporate Communications Section of GRIDCo on November 25, 2026.