The Electricity Company of Ghana (ECG) has announced a planned power outage in parts of the Ashanti Region from Monday, November 30, to Friday, December 4, 2026, to facilitate major transmission infrastructure upgrade works by the Ghana Grid Company Limited (GRIDCo).
The planned interruption, which will affect several communities in Kumasi and surrounding areas, is expected to occur daily between 7:30 a.m. and 5:00 p.m. throughout the five-day period.
According to ECG, the exercise forms part of ongoing efforts to improve electricity supply in the Ashanti Region and strengthen the capacity of the transmission network to meet growing demand.
The outage will enable GRIDCo to continue upgrading the Anwomaso to Ridge Bulk Supply Point transmission line, involving the replacement of the existing 364MVA single-circuit transmission line with a modern double-circuit system rated at 2 × 488MVA, representing a total capacity of 976MVA.
The upgrade is expected to significantly increase the transmission capacity of the line and enhance the reliability of electricity supply to communities and businesses served by the network.
ECG explained that the temporary interruption of power supply was necessary to allow engineers to safely undertake the development works, which are considered critical to improving electricity distribution and transmission infrastructure in the region.
Affected Communities
The communities expected to experience the planned power interruption include Ahenema Kokoben, Sokoban, Daban, Asaago, Ampabame No. 1 and No. 2, Bekwame, Kotwi, Nkoransa, Paa, Kyekyewere, Pakyi No. 1 and No. 2, Brofoyedru, Sabin Akrofuom, Adum Afrancho, Anyinam and parts of Santase.
Other affected areas include Atonsu Kuwait, Naachia, Sawuah, Aprabon and surrounding communities.
Residents, businesses, institutions and commercial operators in the affected areas have therefore been urged to take note of the scheduled outage and make the necessary preparations to minimise the impact of the interruption on their daily activities.
The planned works are expected to provide a stronger transmission backbone for electricity supply in the Ashanti Region, particularly as demand for power continues to increase in residential, commercial and industrial areas.
The replacement of the existing transmission line with a higher-capacity double-circuit system is expected to improve the ability of GRIDCo to transmit electricity more efficiently while strengthening the network against supply challenges.
ECG has expressed regret over the inconvenience the planned outage may cause customers and the general public, assuring that the exercise forms part of efforts to improve power supply infrastructure in the region.
The company has appealed to affected customers to cooperate with the utility companies as the upgrade works are undertaken.
The planned outage is expected to run from 7:30 a.m. to 5:00 p.m. daily from Monday, November 30, to Friday, December 4, 2026.